Area of Expertise - Water...
Meeting the basic need of water is a long-standing challenge in sub-Saharan African countries as it is indeed in many countries of the developing world. It is a challenge that AIC has met to the full being responsible for the design and supervision of many of Nigeria’s most successful projects. The support given by the African Development Bank (ADB) has been instrumental to that success. The Department’s expertise is now being applied to the wider development of projects in African and the Caribbean.
AIC’s recent and current workload on water supply alone comprises over 180mgd of water supply capacity and $1 billion of installed works as indicated in the table.
Project
|
Capacity
Mgd |
Cost
$m |
Bauchi Township |
10 |
70 |
Keffi/Akwanga & Doma |
12 |
75 |
Jos/Bukuru Expansion |
20 |
90 |
Benin city,Warri/Effunrun |
35 |
220 |
Northern Ishan |
10 |
30 |
Yola/Jimeta |
20 |
75 |
Gombe |
15 |
100 |
Ilorin & Jebba |
30 |
140 |
Uyo metropolitan |
30 |
100 |
In these projects the scope of work has required AIC to provide Engineering services to cover:
Subsequent to contract award AIC has been responsible for Project management and site supervision.
KEFFI/AKWANGA & DOMA WATER SUPPLY PROJECT

Client:
Plateau Public Utilities Board
Finance:
African Development bank & Client
Construction cost:
$76 million
Scope of work:
Feasibility study, Design, Tender Documentation, Tender Evaluation. Project Management & Site supervision
The two schemes for Keffi /Akwanga and Doma water supplies were integrated into a single project to serve the three principal towns as well as smaller town and villages in the vicinity. The feasibility study paid particular attention to the determination of population and scheme design capacities.
A full economic and financial appraisal was included for ADB funding negotiations and these showed that the existing tariff structure would not produce an adequate IRR for the project. Proposals were therefore made for a progressive adjustment of tariffs over a ten year period to achieve full cost recovery. The scheme for Keffi/Akwanga is based on raw water extraction from the River Mada and has a peak output of 53,000 cu.m /day
Treatment comprises aeration, clarification, filtration and sterilization using plant designed for robust operation. Raw and treated water pumping plant with a total installed capacity of 160kW is provided .the rising main to Keffi is 54km long and 700/600mmdia ductile iron. The rising main to Akwanga is 13km long and of 300mm dia ductile iron. Altogether five new service reservoirs are provided, feeding new distribution system with a total length of 90km.
The Doma scheme uses the existing Doma irrigation impounding reservoir as its source and has a peak output capacity of 11,500 cu.m/day.
The treatment process is similar to the Keffi scheme. Total installed pump capacity is 400kw and the 300mmdia ductile iron rising main is 11km long, feeding a single new service reservoir. The distribution network has mains up to 400mmdia and a total length of 25km.
Project completion is in April 1995.
-------------------------------------------------------------------------------------------------------------------------------------------
DOMA/LAFIA EXPANSION WATER SUPPLY SCHEME
MARARABAIKARU WATER SUPPLY SCHEME
Client:
Nasarawa State Water Board
Finance:
African Development Bank
Construction Cost:
i. Doma/Lafia Scheme - US$74,415 Million
ii. Mararaba Scheme - US$116,275 Million
Scope of Work:
Feasibility Studies, Environmental Impact Assessment (EIA), Designs,
Tender documentation, Tender Evaluation, Project Management and
Construction supervision.
The Doma/Lafia and Mararaba/Karu water supply Schemes consist of the
following:
Improvement of water supply to Lafia through the rehabilitation of the existing Lafia
treatment works to full design capacity. Construction of a second Doma treatment
works to be sited by the existing Doma irrigation impounding reservoir including a
pumping station, pumped mains to Lafia and new distribution network for Lafia and
Environs.
The Mararaba/Karu Water supply Scheme involves the construction of New
Treatment Works on Uke river consisting of:
- Off-line storage reservoir and associated pumping station
-
Raw water transfer main to the treatment works
-
Treatment works with the following components:
(a) Aeration/Flash mixing
(b) Sedimentation
(c) Filtration
(d) Sterilization/Buffer storage
- Treated water pumping station
- Treated water remains from treatment plant to Mararaba, Karu, Masaka and
Environs
-------------------------------------------------------------------------------------------------------------------------------------------
BAUCHI TOWNSHIP WATER SUPPLY SCHEME
Client:
Bauchi state urban utility board
Finance:
African development Bank & Client
Construction Cost:
$70 million

Scope of work:
Design Audit & Supervision of Turkey Construction contract
The projects consist of construction of water treatment works, distribution system and all necessary mechanical and electrical plant. The water gravities from the existing Gubi Dam intake via twin steel mains to the treatment works.
These works provide 45,500 cu.m/day of treated water in stage 1 and provide for expansion to 70,000 cu.m/day in stage 11.
The treatment process consist of aeration, clarification,
Filtration and final disinfection. Chemical treatment includes provision of automatic and standby gravity dosing of alum, lime and polyelectrolyte. The treated water is pumped to two existing million litre reservoir with a maximum working head of 16 bar surge suppression, an 11kV sub-station and standby power are all provided, as is staff accommodation.
The treated water rising main from the works to the reservoirs is an 800mm dia steel pipeline ,13km long .The distribution system ,incorporating the existing system ,was modeled and verified .The contract includes the laying of approx. 200km of steel mains, varying between 100mm and 700mm in dia.
AIC carried out an Environmental impact Assessment, including sanitation study of existing practices of water supply, sanitation, surface water drainage and solid waste disposal.
-------------------------------------------------------------------------------------------------------------------------------------------
BAUCHI STATE WATER SUPPLY PROJECT
Azare, Misau, and Jama' are Water Supply Scheme
Client:
Bauchi State Water Board
Finance:
African Development Bank
Construction Cost:
US$83 Million
Scope of Work:
Feasibility Study, Environmentatlmpact Assessment (EtA), Designs,
Tender Documentation, Tender Evaluation, Project Management and
Construction supervision.
The Azare, Misau and Jam' are Water Supply Scheme is based on the abstraction
of water from the alluvial aquifer through collector wells to supply Azare and
Jama'are towns and adjoining villages and the construction of the Gulka Dam to
support down-strteam abstraction at Kari to Supply Misau town and adjoining
Villages.
The components of the Scheme consist of:
- Collector wells at Jama' are on River Jama' are to meet water demand in
Jama' are and Azare
-
Ground water storage and chlorination works at River Jama' are Site.
- Pumping main from ground storage to Azare' via Jama' are.
-
A collector well at Kari on the River Misau to serve Missau.
-
Ground storage and chlorination works at River Misau site.
- Pumping main from ground storage to Misau.
- Construction of Gulka Dam to support abstractions from the alluvial aquifer at Kari.
----------------------------------------------------------------------------------------------------------------------------------------
EDO STATE WATER SUPPLY PROJECT
Benin City Water Supply Scheme
Client:
Edo State Urban Water Board
Finance:
African Development Bank
Edo State Government of Nigeria
Construction Cost:
USS152.49 Million
Scope of Work:
Preliminary Design, Final Design, tender Documentation,
Tender Evaluation, Recommendation and Award of
Contract, Construction Supervision of works.
The second phase of the Benin City Water Supply Scheme the upgrading of the
Ikpoba Dam Treatment Plant with the construction of 4No.additional Filter Beds;
diversion of surface water drainage from-upstream to down-stream of Ikpoba
Dam, construction of4No ground level pre-stressed and 2No. Elevated concrete
storage reservoirs, supply and installation of Ductile Iron (DI) pipes of 100mm
diameter for extensi0r1 of distribution system and the supply and installation of
40,000 consumer meters, rehabilitation of 5No existing bore-hole head-works,
supply and installation of electro-mechanical equipment for the upgrading of
Ikpoba Dam treatment Plant, construction of Head-quarters Office building,
Special Area Office, 2NoArea Offices and 1No District Office.
The construction of works commenced in1993 and 1995 when work on site was
suspended due to exhaustion of the African Development Sank (ADS) fund
arising from several unforeseen factors during implementation. During the two
years (1993-1995) of construction works had reached 750/0 overall completion.
Due to various political transactions from Military to Civilian, successive Civilian
Administrations in the State have been making concerted efforts to secure
additional funds to complete the balance works and other new works.
----------------------------------------------------------------------------------------------------------------------------------------
BENIN CITY AND WARRI / EFFURUN WATER SUPPLY SCHEMES EDO AND DELTA STATES
Client:
1. Benin City: Edo State water Board;
2. Warri/Effurun: Delta state water Board
Finance:
African Development Bank & client
Construction cost:
$220million
Scope of work:
Design, Tender Documentation, Tender Evaluation, Construction Supervision
Upgrading of Benin City water scheme, through the improvement of Ikpoba
The Benin City and Effurun water schemes consist of the following.
Dam:
The construction of phase II of the treatment plant: supply and installation of DCI and AC pipes of 100 to 700mmdia: rehabilitation of five boreholes headwords: construction of five booster stations: supply and installation of electro-mechanical equipment: and the supply and installation of meters.
The expansion of Warri–Effurun water scheme involves the construction of three well field and the associated headwork’s: the construction of three treatment plants (aeration, lime dosing and filtration):construction of 13 storage tanks :supply and laying of DCI and AC pipes of 150 to 900mmdia; supply and installation of electro-mechanical equipment.
- Construction of office building, workshop, central laboratory and office facilities.
- Provision of operational equipment such as vehicle, Telecommunications, and computers.
-
Construction of the water supply systems is due for completion in 1995.

-------------------------------------------------------------------------------------------------------------------------------------------
DELTA STATE WATER SUPPLY PROJECT
WarrilEffurun Water Supply Scheme
Client:
Delta State Urban water Board
Finance:
African Development Bank
Delta State Government of Nigeria
Construction Cost:
US$127.05 Million
Scope of Work:
Preliminary Design, Final Design, Tender Documentation, Tender Evaluation,
Recommendation and Award of Contract, Construction Supervision.
The WarrilEffurun Water Supply Scheme was planned for three separate sourcelhead-works
locations of the Warri/Effurun Metropolis namely Dom Domingo source head-works, Uwase
source head-works and Barracks source head-works. The implementation ofthe fIrst phase which is
Dom Domingo sourcelhead-works commenced in 1993 up to 1995 when work was suspended due
to exhaustion of the African Development Bank (ADB) fund caused by several unforseen factors
during implementation. However, due to the various political transition from Millitary to Civilian
administration in 2005, resuscitated the suspended project.
The Dom Domingo source head-works involves the construction ofone well fIelds consisting of I7No.
Bore holes and associated head-works, construction of a treatment plant (aeration, time dosing and
f1ltration), construction of a 45 meter high water tower, supply and installation of Ductile Iron (DI)
pipes of 100mm to I,000mm diameter for distribution network and supply and installation of 30,000
consumer meters and the supply and installation ofelectro- Mechanical plant and equipment.
Construction of INo. Special Area Office, Maintenance Workshop, 3No.Area Offices and 12No.
District Offices.
Provision of operational equipment such as vehicles, telecommunications and computers for the
Project Implementation Unit (PIU).
Construction works on the Dom Domingo source head-works have reached 95% completion and
commissioned on or before June 20 IO.
-------------------------------------------------------------------------------------------------------------------------------------------
OYO STATE WATER SUPPLY PROJECT
Shaki, New Iseyin, Oke- 'Ho, Iganna and Environs Water Supply Schemes.
Client:
Oyo State Water Corporation
Finance:
African Development bank
Construction Cost:
US$206,280 Million
Scope of Work:
Feasibility Study, Environmental ImpactAssessment (EIA), Designs, Tender
Documentation,Tender Evaluation, ProjectManagement and Construction
Supervision.
The Shaki, New Isdeyin, Oke- 'Ho Iganna and environs Water Schemes involves two separate
Schemes namely existing Ikere Gorge Dam supplying water to Iseyin, Oke-Ho, Iganna and
environs and a separate new dam at Sepeteri supplying water to Shaki and environs.
The components ofthe Schemes are:
- Construction ofa new bigger dam on Ogun River at Sepeteri and removal ofthe two smallerExisting dams at Sepeteri.
- Construction ofa treatment plant each at Ikere Gorge and Sepeteri.
- Pumpedtrunk mains from Ikere Gorge and Sepeteri to the outlaying project area.
- Boosterpumping stations at designated locations.
- Distribution networks in the various towns and villages.
-------------------------------------------------------------------------------------------------------------------------------------------
OSUN STATE WATER SUPPLY PROJECT
(i) Ikire/Apomu/lkoyi water Supply Scheme
(ii) Nmew Iwo Water Supply Scheme
(iii) Ede Oshogbo Water Supply Scheme
Construction Cost:
US$75 Million
Finance:
African Development Bank
Client:
Osun State Water Corporation
Scope of Work:
Feasibility Studies Report (FSR), Environmental ImpactAssessment Report (EIA),
Preliminary Design Report (PDR), Detailed Engineering Design (DED) and Drawings,
Tender Documentation, Tender Evaluation, Recommendation ofAward ofcontract,
Project Management and Construction Supervision.
The Scheme for Ikire/ApomulIkoyi and environs involves Asejire Dam abstraction works and Raw
Water pumping station, Raw Water Transfer Main to the Treatment works, construction of a new
treatment works located on the Osun Stae side ofthe existing Asejire Dam comprising aeriation/flash
mixing, flocculation/classification, filtration, sterilization/contact tank, chemical dosing/storage,
Treated Water Pumping Station, Treated Water Transfer main to the Reservoirs, Stand-by Generating
sets and Distribution systems. The construction ofa completely new treatment works to be located on
the Osun State side3 of the existing Asejire Dam complete with low lift and high lift pump sets.
Replacement ofthe existing trunk mains of4500mm diameter Ductile Iron (DI) pipes and extensive
distribution net work.
The Scheme for Iwo township including the Bowen University campus, Oluponna, Ogbagba,
Telemu, He Ogbo, Kuta and environs involves the construction ofa new water works using River Oba
as the new source ofraw water. This new water is provided by the impoundment ofRiverAyiba cannot
meet up with the required volume ofwater for the new Iwo Water Supply.
The Ede/Oshogbo water Supply Schemes requires the rehabilitation of the existing electromechanical
equipment at both the old and new water works. Desilting ofthe water catchment areas of
the dam is required to restore design capacity ofthe dam.
|